Omaha CSO

Skip to content
Omaha CSO logo
  • Home
  • About the Program
  • Contractors' Corner
  • Program Projects
    • Project Map
    • Design
    • Construction
    • Completed
    • Future
    • Green Infrastructure
  • Public Meetings & Outreach
  • Home
  • About the Program
  • Contractors' Corner
  • Program Projects
    • Project Map
    • Design
    • Construction
    • Completed
    • Future
    • Green Infrastructure
  • Public Meetings & Outreach

Quick Links

  • Contractors' Corner
  • E-Learning
  • Quarterly Report
  • Interactive Project Map
  • Program Spotlights & Video Gallery
  • Long Term Control Plan & Updates
  • Green Infrastructure
  • Contact Us
  • Home
Construction image

construction-icon

Construction Projects*

Click on the links below to learn more about projects currently under construction. These projects have been bid and a contractor has been awarded the construction contract. The projects are maintained as active on this page until the project has reached final completion and the construction contract is closed. Each project page includes a map of the project area, information about the project, key project contacts, and approximate schedules for implementation.

The Riverview Lift Station Replacement Project is 97% complete. Installation of final electrical equipment is expected in Q1 2023.

Photo of ProjectMissouri River Water Resource Recovery Facility - Transfer Lift Station Pump ReplacementBridge crane installation was completed Q4 2022.

cost.png$6,583,000

time.png93% complete

Photo of ProjectRiverview Lift Station ReplacementInstallation of final electrical equipment is expected Q1 2023.
(Blake Street Lift Station Improvements was added as a contract change order.)

cost.png$25,500,000

time.png97% complete

ConstructionThumb_PCN210.jpgPapillion Creek North (PCN) 210 Sewer Separation ProjectWinter shutdown began in December; the spring restart will include change order items.

cost.png$8,087,000

time.png97% complete

ConstructionThumb_CC203.jpgCole Creek CSO 203 Sewer Separation ProjectPaving work continued in Q4 2022; winter shutdown began in December and will restart in spring 2023.

cost.png$7,415,000

time.png76% complete

Photo of projectSaddle Creek Retention Treatment BasinPermanent power and exterior paving completed Q4 2022.

cost.png$92,400,000

time.png92% complete

ConstructionThumb_NicholasStPh3B.jpgNicholas Street Sewer Extension – Phase 3BStreet paving and M.U. D. water main construction continue.

cost.png$21,000,000

time.png30% complete

ConstructionThumb_MonroeLS.jpgMonroe Street Lift Station Improvements ProjectDemolition work continues in pump rooms; electrical room work is ongoing.

cost.png$25,200,000

time.png24% complete

Photo of projectForest Lawn Creek Inflow Removal and Outfall Storm Sewer ProjectExpecting construction notice to proceed March 2023.

cost.png$34,400,000

time.png0% complete

Photo of ProjectBlake Street Lift Station ImprovementsGravity sewer installation completed Q4 2022.
(Added as a contract change order to the Riverview Lift Station Replacement Project.)

cost.png$4,291,000

time.png38% complete

Updated February 2023

 *Includes projects bid (or advertised for bid) for construction and other City-related sewer separation projects that are not part of the Long Term Control Plan. Costs reflect CSO Funding, but do not include other project funding sources.