Saddle Creek Retention Treatment Basin Project


Schedule

Construction anticipated to begin in 2019.

Project Description

The Saddle Creek RTB is an important project for Omaha’s water quality program called Clean Solutions For Omaha. Over 65 times a year untreated combined sewage overflows into the Little Papillion Creek from the sewer outfall at the project location. The purpose of the Retention Treatment Basin facility is to capture this water and treat it during wet weather. This project began planning and design activities in April of 2011 and is proposed to be constructed at 64th and Dupont Streets in Omaha.

The facility will operate during rain events. If it is a small rain event, the combined sewage may be retained and sent to the Papillion Creek Water Resource Recovery Facility (PCWRRF) for treatment. When the rain event exceeds the capacity of the RTB, the combined sewage will be treated, disinfected, and then discharged to the creek.

Combined sewage will be diverted from an existing outlet channel to the facility headworks where large materials like cans, rocks, tree branches and floatable solids are removed using a grit pit and mechanical screens. At this point in the process, a disinfectant is added. If the tank fills up, an overflow channel is provided for discharge of treated flow back to the creek.

The RTB will use pumps to empty the facility after a rain event has ended. The dewatering pumps will convey captured combined sewage volume into the downstream Papillion Creek Interceptor sewer for additional treatment at the PCWRRF.

Above ground improvements include a building to house controls, grit and screening equipment, and chemicals. The building, illustrated above, will provide office space for full-time staff, some additional city offices, and maintenance access to the facility.

An odor control system will be installed to address the risk of odors being released to the surrounding area. The site will include fencing and lighting for security purposes. Deliveries will occur regularly, but are not expected outside of typical business hours.

This project was originally bid in 2015, and the City elected not to proceed with construction of the facility at that time. To keep the project moving, a site preparation project was identified to remove buried construction and demolition (C&D) debris. This work was completed in June 2016 and reduces the amount of site preparation required for the larger facility project.

Simultaneously, a process of Value Engineering (VE) was undertaken in 2016 to examine items that could be changed to reduce the cost of the project. Recommendations included revisions to reduce cost while maintaining the required water quality performance.

The Saddle Creek RTB facility is currently being re-designed to incorporate cost savings recommendations, and the project will be re-issued for bid. Changes from the original project concept include a 50 percent reduction in the storage basin volume and incorporating a simpler pump station within the larger tank structure.

Rendering
 
 
 
 
 
 

Project References

Project Number: OPW 52049
LTCP Project Name: Saddle Creek CSO 205-64th and Dupont RTB

Additional Resources

Preliminary Design Public Involvement Meeting – August 22, 2013
Aksarben-Elmwood Neighborhood Meeting – May 15, 2014

What is a RTB? – animation